Case 1: An Mexican Multi-Project Real Estate Company engaged in Residential Township Development

Illustrative Scenario: Multi-Township development projects across different cities of Mexico

 

Before

After CCPM implementation


  • Total Chaos in the Project Planning dep't producing almost all projects for execution incomplete leading to massive rework

  • Each project in planning dep't was taking 3-4 months with many missing components

  • Long Review meetings without any conclusions

  • Quality suffering due to the certain gaps in the desired and actual work done by the company

  • No visibility regarding the individual projects completion date due to the working of employees in silos
  • Project Priority with checklist for all steps in the project planning and execution put in place leading to greater visibility in the status of different projects

  • Each week one project complete in all respects produced by project planning dep't

  • PMO established with strong weekly update system, MIS generated for top management feedback

  • High Quality due to Culture of working as per Full Kit installed in all depts. of the Company

  • All projects of the company uploaded on the central server. The projects progress updated weekly with clarity regarding the completion date of each project