Case 2: An Indian Real Estate Company engaged in Residential and Commercial Complexes

Illustrative Project: Residential complex - Five Towers of 50 Floors each targeted at High Income segment (Initial Time frame 3 years)

 

Before

After CCPM implementation


  • Clear indications that there will be at-least two years delay in the project i.e. now the project timeline became 5 years

  • Neither the Project Constructor or the Project Management Company was not committing any time line

  • Long Review meetings, rampant blame game

  • Delayed Decisions by Management

  • Constant changes in drawings and specifications

  • Huge labour absenteeism at the site

  • Each floor was taking anywhere between 15 to 21 days

  • CCPM review everyday by the CEO for only 15 minutes

  • Focus of the review on corrective actions rather than analysis and finding the culprit

  • Decisions given within 24 hours

  • Full-kitting of drawings, permits and specifications,

  • No more labour absenteeism because of measurement change and win-win offer

  • Time for each floor brought down to 7 days

  • Three towers completed well within time, the other two expected to complete much before the initial time line of 3 years