Case 3: A Pharmaceutical Company - Capacity Elevation

Illustrative Project: Capacity Elevation of existing plant to create eight building each for a specific purpose

 

Before

After CCPM implementation


  • Projects started a year ago, with less than 5% progress in each

  • Neither the Project Constructor or the Project Management Company was not committing any time line

  • Long Review meetings, rampant blame game

  • Delayed Decisions by Management

  • Constant changes in drawings and specifications

  • Huge labor absenteeism at the site


  • Eight expansion projects executed within 9 months.

  • Projects completed with a successful target lead time reduction of 25%.

  • Top Management has clear visibility of the status of each project and the tasks of each project which are blocking progress.

  • Top Management has clear visibility wrt to the staggering of projects depending upon the finances available. As a result a project started flows smoothly to completion.

  • All projects were executed on schedule


New Project: Building the project plan for a office campus for this Pharma company in Hyderabad, starting with a basement 1&2 and 3 floors. Eventual plan is to build 3 towers of 16 floors each in addition to the basement.